| Free Case Study Of the Boeing 7E7 Project Essay

Boeing 7E7 Case Study Example_x000D_
_x000D_
The plan to design and sell Boeing 7E7, Dreamliner, began in early 2003. However, there were news of a depressed market which expressed a sharp contraction for more than six months. During this time, the U.S. was at war with Iraq, which led to shocking news headlines concerning global terrorism. Together with the breakout of a deadly disease known as SARS, the industry run into losses, which was the worst experienced in the aviation industry. The situation proved to be a challenging one to initiate the project._x000D_
_x000D_
_x000D_
_x000D_
_x000D_
_x000D_
Type of assignmentWriter levelTitle of your paperPages_x000D_
Essay Term paper Coursework Research paper Research proposal Grant Proposal Case Study Case Brief Discussion Board Post Reaction paper Response paper Literary analysis Article Review Article Critique Movie Review Movie Critique Book Report Book Review Synopsis Poem Letter Motivation letter Memo Scholarship essay Article writing Blog Article Annotated Bibliography Literature Review Outline Online Test Questions-Answers Multiple Choice Questions Interview Questionnaire Speech Dissertation Dissertation chapter – Abstract Dissertation chapter – Introduction Dissertation chapter – Hypothesis Dissertation chapter – Literature review Dissertation chapter – Methodology Dissertation chapter – Results Dissertation chapter – Discussion Dissertation chapter – Conclusion Thesis Thesis Proposal Thesis/dissertation chapter Capstone Project IB Extended Essay Lab Report Business Report Business plan Marketing Plan White paper Formatting Editing Proofreading Rewriting Revision Powerpoint Presentation Powerpoint Presentation Poster PDF Poster Excel Exercises High School College University Master’s PHD 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 348 349 350 351 352 353 354 355 356 357 358 359 360 361 362 363 364 365 366 367 368 369 370 371 372 373 374 375 376 377 378 379 380 381 382 383 384 385 386 387 388 389 390 391 392 393 394 395 396 397 398 399 400 401 402 403 404 405 406 407 408 409 410 411 412 413 414 415 416 417 418 419 420 421 422 423 424 425 426 427 428 429 430 431 432 433 434 435 436 437 438 439 440 441 442 443 444 445 446 447 448 449 450 451 452 453 454 455 456 457 458 459 460 461 462 463 464 465 466 467 468 469 470 471 472 473 474 475 476 477 478 479 480 481 482 483 484 485 486 487 488 489 490 491 492 493 494 495 496 497 498 499 500 _x000D_
SpacingTimeframesCurrencyTotal price_x000D_
Single spaced Double spaced 11 days 9 days 7 days 5 days 4 days 3 days 48 hours 24 hours 12 hours 8 hours 6 hours 3 hours USD EUR GBP AUD _x000D_
_x000D_
_x000D_
_x000D_
_x000D_
_x000D_
However, the in mid 2003, Michael Brier, the head of the design team made announcements that the project was progressing on well and was continuing to be on track to provide the brand. The head of the design team seek from the Board of Directors of Boeing to proceed with their intended project, which would lead to the collection of orders from airlines to finish the valuation of the Boeing 7E7 and expect the airplane to start operating in 2008. Thus, the valuation of the project was to be completed by the Board of Directors to obtain a go ahead from the top executive and other senior management. This study seeks to demonstrate if the project financial analysis would yield a better outcome to the Boing 7E7 shareholders._x000D_
_x000D_
Origins of Boeing 7E7 Dreamliner_x000D_
_x000D_
Before rolling out the successful Boeing 777 in 1994, Boeing had not introduced any new commercial airline. However, in 1990’s the company made a major announcement that it had done away with the plan to design a new commercial airplane. One of the projects was to design a Sonic Cruiser which had the capacity to fly faster than all other commercial airlines. However, the company faced a major drawback after two years when the potential |ers provided their feedback that they were not willing the premium price intended for the faster flight. This led the company into a major financial crisis to gain some of the commercial airplane gains that it had previously lost in Airbus, which proved to the main rival in the industry._x000D_
_x000D_
However, with major advancements in three technology areas, the company managed to design the Boeing 7E7 Dreamliner which proved to be efficient. The company’s executive directors observed that the brand would be a success and would carry many passengers and was also able to make short flights. The other advantage was that the airplane was able to consume less fuel than the existing airplanes and would turn put to be cheaper than its rivals. This was a time when the industry players were struggling to make profits, consume less fuel, and operate with cheaper operating costs, coupled with both short and long distance flexibility which would provide an attractive package for travelers at an affordable price._x000D_
_x000D_
Boeing 7E7 Brand_x000D_
_x000D_
Therefore, to make the airplane more efficient, the Boeing 7E7 brand was to be the first airplane to be made from carbon reinforced material which was supposedly stronger and lighter than aluminum. In addition, the use of these would also reduce the manufacturing costs. The main goal of the design team was to come up with an aircraft with fewer components that would be assembled in less days. However, the plan had its risks._x000D_
_x000D_
First, the composite materials were suspected to be the main reason behind the 9/11 plane crash; next the executive called for a radical change to alter its production method. Boeing made the last production change in 1997, to minimize its operating and production costs. However, the process never succeeded resulting into the closure of the production line, as well as, missing of airline deliveries. However, the only possibility was to consider the snap on the wing-extensions. However, the main challenge was whether the plan would be feasible or costly._x000D_
_x000D_
In 2002, the airline industry was dominated by two large commercial aircraft. These were the Boing and the Airbus. However, Boeing held the lead in the commercial aviation market, but the Airbus managed to the number one airplane. In the year 2002, Airbus many commercial orders compared to Boeing’s orders. In addition, while Boeing was working hard to meet the future demands for a midsized brand, the Airbus made announcements of its A380 which would turn out to be the largest commercial aircraft ever to be designed._x000D_
_x000D_
_x000D_
_x000D_
_x000D_
_x000D_
Boeing was later split into two primary segments, the commercial airplane and the Integrated Defense system. The company was later awarded $16.6 million to provide defense contracts. In the year 2002, these primary segments each earned the company an almost similar figure on aircraft revenues. In addition, while the commercial aircraft revenues had been reducing the revenues obtained from defense were increasing drastically. Thus, the company benefited from a significant technology transfer from the Defense R&D to be integrated into the commercial aircraft segment._x000D_
_x000D_
In the short-term, the demand for the airline was influenced by the business cycle, as well as, consumer confidence. On the other hand, in the log-run, the business cycle smoothed out, as well as, the GDP, international trade. The concept of the Boeing 7E7 was triggered by |er demands. In 2001, the company had an original plan to design the Sonic Cruiser, an airplane which was intended to have the fastest speed of sound; however, the challenge was whether the |ers would be able to afford the premium price for the services. Consequently, loyal |ers to the plane who had shown interest in the cruiser based their focus on survival strategies. Therefore, the company anticipated an increase in demand for between 2000 to 3000 airplanes. However, the demand for Boeing 7E7 depended on whether the company would deliver the a reduction in fuel costs, as anticipated, coupled with the range flexibility in a the design of a medium sized aircraft._x000D_
_x000D_
Financial Forecast and Analysis_x000D_
_x000D_
The following was a forecast of Boeing’s cash flows from the project and is consistent with the public information which was provided by the company. The primary implication of the financial forecast is that the project would result into an Internal Rate of Return which is closer to 16% the assumption made was that the company would not only deliver the promised brand, according to the specifications demanded by the clients, but it was also anticipated that the main rival would not be able to replicate Boeing’s efficiencies. It was also estimated that the value would be placed on the number of passengers. Therefore, by applying this methodology without any premium for cost reduction, the minimum price for the Boeing 7E7 and the entire stretch of airplanes would cost $ 114,5 million and $144.5 million respectively. The assumption made in the forecast is that passengers would be able to afford and pay a 5% price premium for the lower operating cost._x000D_
_x000D_
Internal Rate of Return for Boeing 7E7 Dreamliner_x000D_
_x000D_
The assumption made was that the IRR which was in line with the base case assumptions was 15.7% However, the estimated IRR was very sensitive to changes in various assumptions made. It was obvious that certain uncertainties would be based on the number of units that the company was willing to sell and at an appropriate price. The other aspects which were unknown comprised of the development costs, coupled with the per-copy cost to design the Boeing 7E7 brand. It was assumed that the company would require $8 billion to be used in the development costs. In addition, this cost was also subject to uncertainty. The other challenge was faced by the engineers in feasibility design a medium sized aircraft having low-range capabilities. However, it was anticipated that the engineering design to achieve this this would lead to pushing up the costs significantly. It was also forecasted that if the company has succeeded in making use of the composite materials, then the construction materials would be reduced._x000D_
_x000D_
_x000D_
_x000D_
Talk to an operator NOW! _x000D_
_x000D_
Boeing WACC: 7E7 Cost of Capital_x000D_
_x000D_
The WACC of Boeing would be ascertained by using the following formula which is well understood_x000D_
_x000D_
WACC= (Percent Debt) (rd) (1-Tc) + (percent Equity) (re)._x000D_
_x000D_
rd=Pretax cost of debt capital_x000D_
_x000D_
tc=marginal effective corporate tax rate_x000D_
_x000D_
Percent debt= Proportion of debt in a market value capital structure_x000D_
_x000D_
re= cost of equity capital_x000D_
_x000D_
Percent equity= proportion of equity in the market value capital structure_x000D_
_x000D_
Therefore, based on the given formula, the equity risk premium should have the same values to the excess return expected from shareholders on the market portfolio, which was ascertained as 7.14, and the WACC was ascertained to be 15.443%. In addition, the IRR should also be at least equal to WACC._x000D_
_x000D_
Boeing 7E7 Case Study Conclusion_x000D_
_x000D_
The aviation industry is rampant with a magnitude of risks which are posed by the launching of the new airplane brands. This is associated with huge upfront capital costs in an environment which is embodied by intent technological developments as well as, price competition. Therefore, after a careful consideration of the risks and benefits associated with the Boeing 7E7 project, it was highly recommended that the board approved the project. However, there are risks which may accrue from the design and the selection of the material used in the design material used. The financial reports indicate that there is a better chance for the project to improve the wealth of the shareholders.

Our guarantees

Study Acers provides students with tutoring and help them save time, and excel in their courses. Students LOVE us!No matter what kind of essay paper you need, it is simple and secure to hire an essay writer for a price you can afford at StudyAcers. Save more time for yourself. Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

Our Homework Writing Disciplines

With a highly diverse team in almost all academic fields including: